California mechanics lien checklist for reviewing the form and deadline

Use this checklist to review a California mechanics lien form, required notice, claim details, recording deadline, and the 90-day foreclosure deadline.

By · Published · Updated

Important: This guide provides legal information, not legal advice. Verify deadlines and forms with the county recorder, current California law, or a construction attorney.

If you are preparing or checking a California mechanics lien, focus on three things first: whether a Preliminary Notice was required and timely served, whether the claim includes the required information, and whether the lien was recorded before the deadline.

The form matters, but the form alone does not create lien rights. The California Contractors State License Board says many lien claims are invalid because required filing timelines were missed. CSLB also says a lien may be invalid if the work was not completed or the supplies were not included in the plans or contracts.

In California, a mechanics lien is commonly called a Claim of Lien. Levelset offers a downloadable template labeled “California Mechanics Lien Form (Claim of Lien)” and describes its free forms as fillable PDFs.

A template can be a starting point, but you still need to confirm that the notice, content, and deadline rules were met. CSLB points readers to California Civil Code sections 8000 through 9566 for the mechanics lien statutes.

The checklist that usually decides whether the lien works

Use this list whether you are filling out a claim or reviewing one recorded against your property.

Preliminary Notice: who had to send it and when

This is one of the first things CSLB says to verify.

Direct contractors and laborers do not have to give a Preliminary Notice. Subcontractors and material suppliers do. CSLB states that a subcontractor or material supplier has 20 days after beginning work or delivering materials to serve the notice.

CSLB also states that the notice may be delivered in person or by certified, registered, or first class mail before work begins or supplies are delivered and up to 20 days afterward.

If the notice is late, lien rights are cut back. CSLB says the claimant loses lien rights for work done or materials delivered more than 20 days before the notice. In other words, the claim is valid only for work done or supplies delivered 20 days before notice was given and anytime thereafter.

So if the claimant was a subcontractor or material supplier, and no timely Preliminary Notice was served, that is a serious defect.

What the lien claim should include

CSLB says the claim should include:

CSLB also says the Notice of Mechanics Lien should accompany the lien claim. If you are reviewing a recorded lien, do not look only at the claim page. Check whether the notice and proof of service were included as well.

Recording deadline: 90 days unless a Notice of Completion shortened it

CSLB says the potential lien claimant must record the mechanics lien within 90 days of one of these events:

That 90-day deadline can become much shorter if a Notice of Completion was filed.

CSLB says homeowners have 15 days from the date of completion to file a Notice of Completion. If that notice is filed, the time to record a mechanics lien is reduced:

When you check the deadline, answer these two questions together: was a Notice of Completion filed, and what was the claimant’s role on the project? Those answers determine whether the recording deadline was 90, 60, or 30 days.

After recording, there is another 90-day deadline

Recording the lien is not the end of the process. CSLB states that a lien foreclosure action must be filed within 90 days after the mechanics lien was recorded. A lien foreclosure action is the lawsuit used to foreclose the lien.

CSLB also notes that anyone can record a mechanics lien, but an unlicensed contractor cannot foreclose on a mechanics lien if the work is valued at more than $500.

Problems that often make a recorded lien vulnerable

A few issues come up repeatedly in the CSLB materials:

Any one of those problems can change whether the lien is enforceable.

If you are the property owner and the lien appears invalid

A recorded lien stays in the county records and on the property title until action is taken to remove it. CSLB says even an invalid lien can make it difficult or impossible to sell, refinance, or obtain a line of credit on the property.

If the claimant failed to follow the required time frames, CSLB says the owner can petition the court to remove the lien. Before that, CSLB says the owner should send the claimant a written request by certified, registered, or express mail and keep a copy of the letter and postage receipt.

That request should identify the specific ways the lien failed the checklist, ask that the lien be removed, and remind the claimant that a court can award reasonable attorney fees to release the lien. CSLB explains that the law changed on July 1, 2012, removing the former $2,000 cap on attorney fees.

If the claimant does not remove the invalid lien, and the time has expired to record the lien and to file the foreclosure action, CSLB says the owner may petition the court for a decree releasing the property from the lien.

This article is general information, not legal advice.