how to fill out california preliminary 20 day notice
Filling Out a California Preliminary 20-Day Notice
Complete a California preliminary 20-day notice with the right project details, recipients, deadline, and mailing method to preserve lien rights.
Start with two points: who must receive the notice, and whether you are still within 20 days of first furnishing labor or materials. If either one is wrong, the notice will not do its job.
A California preliminary notice, also called a 20-day notice, tells the people in charge of payment who you are, what you are providing on the project, who hired you, and the estimated value of that work or material. It is an informational notice, not an invoice and not a mechanics lien. For many claimants, sending it is necessary to preserve mechanics lien, stop notice, or payment bond rights. The California Contractors State License Board says subcontractors and suppliers who do not provide the notice lose lien rights, and the timing rule appears in the California Civil Code.
What to enter on the form
Use a California preliminary notice form that matches the state statute. Then fill in the basic project and payment-chain information the notice is meant to provide:
- your business name and contact information
- your role on the project, such as subcontractor, material supplier, or equipment lessor
- a short description of the labor, materials, equipment, or services you are providing
- the party who hired you
- the project address or other information that clearly identifies the job
- the estimated value of your contribution
If the form asks for an estimated amount, give a good-faith estimate. The notice is there to identify your place on the job and the scope of your contribution.
The recipient list depends on the project and your role
Before you finish the form, make sure you know whether the job is private or public. That changes who must receive the notice.
For private projects:
- Subcontractors, material suppliers, and equipment lessors send the notice to the owner, the prime contractor, and the lender if there is one.
- General contractors send the notice if the job has a lender on it. CSLB states that the prime contractor must provide preliminary notice to the construction lender if the project is financed by a loan.
For public projects:
- General contractors are not required to send preliminary notice.
- Subcontractors, material suppliers, and equipment lessors send the notice to the public agency in charge, the prime contractor, and the surety if there is one.
If a required recipient is left out, the notice may not protect your rights against that party.
The 20-day deadline is part of filling it out correctly
The notice must be sent no later than 20 days after you first furnish labor, materials, or other covered work to the project. California Civil Code section 8204(a) is cited for that rule. CSLB also states that a subcontractor or supplier can give the notice before delivering supplies or starting work and up to 20 days after.
That means you do not need to wait until work starts. You can send the notice early, and that is usually the safer move.
A late notice is only partially effective. CSLB explains the consequence more specifically: if the notice is given later, the claimant is only entitled to foreclose a lien for payments owed for work or materials furnished 20 days before receipt of the notice and any time after that. In practical terms, a late notice does not preserve the same rights as a timely one.
A hypothetical example: a supplier first delivers materials on June 1 and mails the notice on June 30. That notice is late. It is not useless, but it does not preserve the full range of rights that a timely notice would have preserved.
Send it by a valid statutory mailing method
The delivery method matters. Sources citing California Civil Code section 8110 state that California preliminary notices must be sent by:
- registered mail
- certified mail
- express mail
- overnight delivery by an express service carrier
For this notice, service is part of validity. Keep a copy of the completed notice and proof of mailing together in your records.
A practical order for completing and sending it
If you are filling out the form from scratch, this order keeps the main errors from creeping in:
- Identify whether the project is private or public.
- Confirm your role on the project.
- Enter your business name and contact information.
- Name the party who hired you.
- Describe what you are furnishing in short, specific terms.
- Add the project address or other clear project identification.
- State the estimated value of your contribution.
- Send the notice to every required recipient using a valid mailing method.
- Save the completed notice and proof of mailing.
What this notice does and does not do
Sending a preliminary notice does not create a lien by itself. It preserves rights that may matter later if payment is not made. If payment problems develop, the deadlines for a mechanics lien, stop notice, or bond claim are separate from the 20-day notice deadline.
Related guides
- California Preliminary 20-Day Notice: What Contractors Need to Know
- California Mechanics Lien Deadlines: Preliminary Notice, Recording, and Enforcement
- How To File A Preliminary Notice In California